Phase 2 work is rapidly coming to a close as the construction crew is making up for lost time and wrapping up final details. Things are happening so fast, photos from two weeks ago are “outdated” (see above)!

Thanks for your patience in waiting for this overdue update. BBS welcomed 4 new students to the upper grade class (two new families moved to Camp Sherman in December) and we received a new mobile unit to accommodate the larger group. We can’t wait to move into the rest of the building and are on track to do so in February!

Read on to see all that’s been completed since the last bond update.

November 2024

⇒ Phase 2 roof dried-in, ready for winter weather

⇒ Phase 2 mechanical, electrical, and fire alarm rough-in

⇒ Phase 2 insulation and drywall

⇒ Phase 2 siding continues throughout the month: vapor barrier, thermal insulation and rain screen installed

⇒ Windows installed on upper east wall of MPR and in new addition

 

Students gave this sweet note to the crew before Thanksgiving

December 2024

⇒ Siding continues through December

⇒ Phase 2 drywall complete

⇒ Phase 1 permanent exterior doors installed (replacing the temp doors from Sept)

⇒ Phase 2 interior paint complete

⇒ Phase 2 heating units installed (heat pump mini splits)

⇒ Bathroom floors: grind & polish complete

⇒ Sidewalks and curbs poured & complete

⇒ Cabinets and casework installed in 3rd classroom

⇒ Phase 1 punch list items wrapped up during winter break

A last look at the red roof overhang that once covered the exterior sidewalk - now concealed inside the ceiling grid of the new interior hallway (Dec. 18th)

January 2025

⇒ Exterior siding & trim complete

⇒ Facia and gutter metal work

⇒ Phase 2 flooring installed – carpet and tile

⇒ Final lighting and electric trim out

⇒ Final plumbing and bath accessories installed late Jan.

⇒ Final heat duct insulation

⇒ Phase 2 ceiling tile complete

⇒ Pavers to be installed late Jan.

⇒ Second office in Phase 1 transitions to final design (temporary pass-through will be closed up when bathrooms are usable upon occupancy)

⇒ On track to move into rest of building in February!

New permanent front door and adjacent window installed (replacing the temporary door)

Windows installed and building wrapped by late Oct.

Siding installation continues through Dec.

Exterior doors on back (south side) of building

View from the front entrance shows plastic barricade blocking construction zone

Plastic (temporarily) removed - there's a hallway!?

Flooring installation Jan. 15th

Sinks installed opposite bathrooms in extended learning space

New storage and windows in the MPR

New library is taking shape with casework and carpet

Additional window added on front office

Site prep for pavers

Paver installation

New modular unit delivered early Dec. to accommodate a growing upper grade class with 4 new students (11 total)

Snow removal took up extra time in mid-December

Gutter & facia work in January

Temp wall (and pass-through to K/1) in the second office of Phase 1 (Jan 16th)

Temp wall removed as this transitions to the final design (Jan 20th)

Flooring installed in extended learning space

New classroom nearly ready

Bathrooms!

View toward the back door with new classroom on right